Skip to content
Release: Australia · Updated: 2026-03-12 · Official documentation · View source

Create a baseline

A Planned Task Baseline is a record of the start and end times of the planned task at a particular moment in time.

To create a baseline, navigate to the form of the top planned task and select the Create a Baseline related link:

Image omitted: PTBaseline.png
Create baseline for the current task.

To view the baseline, configure the related lists to add a related list of baselines:

Image omitted: PTBaseline2.png
Baseline related list

The baseline can be viewed on a Gantt Chart using the related link.

Parent Topic:Extending the Task table with Planned tasks