Create a change task in Service Operations Workspace

When you need to engage another team or agent for help, create and assign change task. For example, there can be tasks to plan the change, implement the change, and test, and review the work.

Before you begin

Role required: itil or admin

Procedure

  1. Open a change request.

  2. On the change record page, Click the more actions icon (

Image omitted: more-actions-icon.png
more actions icon\) and select **Create Change Task**.
  1. In the Create Change task dialog box, select the task type.

    By default, the following task types are available. To create additional task types, see Create a task type for problem or change in Service Operations Workspace.

    • Planning
    • Implementation
    • Testing
    • Review
    • Click Create.
  2. On the form, fill in the fields.

NameDefinition
Short descriptionA summary of the task.
DescriptionDetailed description of the task.
NumberAuto-generated identification number for the task.
Change requestAssociated change request.
StateState of the change task:- Pending: Open and unassigned - Open: Open and unassigned - In progress: Open and actively being worked on - Closed: Inactive and closed. Requires close code and close notes to be provided. - Canceled
Configuration itemConfiguration item \(CI\) or service that the change task applies to.
TypeType of change task, Planning, Implementation, Testing, or Review. The default workflow generates tasks in type Review.
On holdOption to indicate whether the change task is on hold. Provide an On hold reason if a change task is placed on hold.
Assignment
Assignment groupGroup that the change task is assigned to.
Assigned toUser that the change task is assigned to. If an assignment rule applies, the change task is automatically assigned to the appropriate user or group.
Schedule
Planned start dateDate you plan to begin working on the task.
Planned end dateDate the change task is planned to be completed.If the task type is Implementation, the Planned start date and Planned end date values must fall within the planned start and end dates specified in the change request.
  1. Click Save.

Parent Topic:Change Management in Service Operations Workspace

Related topics

Create a change request in Service Operations Workspace

Work on a change request in Service Operations Workspace

Standard change catalog

Work on a change task in Service Operations Workspace

Create a Change Advisory Board (CAB) definition

Create a CAB meeting

Conduct a CAB meeting in the CAB workbench