Holiday schedules in a release

You can associate a holiday schedule with a release so that the phase and release durations are calculated considering non-working days.

The following example of a release shows how holiday schedules affect its overall timeline to keep important dates on working days.

Let's say a release has 4 phases: Planning, Development, Testing, and Implementation, with durations of 10, 25, 15, and 10 days, respectively, totaling 60 working days. The release readiness target date is set to Sep 5, 2025, and has a public and weekend holiday schedule (U.S. Federal + Weekend holidays in 2025) associated. So, the start and end dates of each phase are adjusted to account for non-working days (holidays and weekends on the schedule), to keep the phase durations intact. Key dates also follow the same adjustment rule.

  • Considerations:

    • Total release duration: 60 working days
    • Phases and durations: Planning: 10 days; Development: 25 days; Testing: 15 days; Implementation: 10 days
    • Release readiness target date: Sep 5, 2025
    • Working days in a week: Mon through Fri (5 days)
    • Non-working days on the associated schedule:
      1. Weekends are non-working days so skipped.
      2. Federal holidays in 2025, relevant to the release period are as follows:
        • Jun 19: Juneteenth (Thu).
        • Jul 4: Independence Day (Fri).
        • Sep 1: Labour Day (Mon).
    • Adjustment rules:
      • The original end date of the last phase is the release readiness target date, usually a working day so no adjustment needed. For all phases before the last, original start and end dates are derived by counting consecutive calendar days, regardless of whether they fall on working or non-working days. Their adjusted end and start dates are the actual dates on a working day, skipping non-working days.
      • The original start date is determined by counting all calendar days backward from the adjusted end date. The adjusted start date is the actual start date on a working day, skipping non-working days.
      • If a key date or the phase start or end date falls on a holiday or weekend, shift to the previous working day.
      • The duration of each phase (in days) remains fixed, but holidays and weekends within the phase period extend the calendar span. With these considerations, let's calculate the working days in the release timeline and adjust the phase and release duration accordingly.
  • Calculation of release dates with holiday adjustments

OptionDescription
PhasePhase 4: Implementation
Original end dateSep 5 \(Fri\)\(Same as the release readiness target date\)
Adjusted end dateSep 5 \(Fri\)\(A working day, no adjustment needed\)
Original start dateAug 27 \(Wed\)\(10 days counted backward from the phase's adjusted end date, includes weekends and holidays\)
Adjusted start dateAug 22 \(Fri\)\(excludes weekends and holidays, see the End date calculation\)
Key datesDeployment preparation: On fifth day from the phase's adjusted start – Aug 28 \(Thu\)\(Excludes weekends and holidays. Falls on a working day, no adjustment needed\)
Original duration10 daysAug 27 \(Wed\) – Sep 5 \(Fri\)
Adjusted duration15 calendar days \(10 working days + 5 non-working days\)Aug 22 \(Fri\) – Sep 5 \(Fri\)
End date calculationWorking days: 10- Sep 5–2 \(Fri-Tue\): 4 days. - Aug 29–25 \(Fri-Mon\): 5 days \(total 9 days\). - Aug 22 \(Fri\): 1 day \(total 10 days\). Non-working days: 5 - 1 holiday skipped: Sep 1 \(Labor day\) - 2 weekends skipped: Aug 30-31; Aug 23-24
OptionDescription
PhasePhase 3: Testing
Original end dateAug 21 \(Thu\)\(The day before the Phase 4 start date\)
Adjusted end dateAug 21 \(Thu\)\(A working day, no adjustment needed\)
Original start dateAug 7 \(Thu\)\(15 days counted backward from the phase's adjusted end date, includes weekends and holidays\)
Adjusted start dateAug 1 \(Fri\)\(Excludes weekends and holidays, see the End date calculation\)
Key datesTest plan approval: On fifth day from the phase's adjusted start – Aug 7 \(Tue\)\(Excludes weekends and holidays. A working day, no adjustment needed\)
Original duration15 daysAug 7 \(Thu\) – Aug 21 \(Thu\)
Adjusted duration21 calendar days \(15 working days + 6 non-working days\)Aug 1 \(Fri\) – Aug 21 \(Thu\)
End date calculationWorking days: 20- Aug 21-18 \(Thu-Mon\): 4 days. - Aug 15–11 \(Fri-Mon\): 5 days \(total 9 days\). - Aug 8-Aug 4 \(Fri-Mon\): 5 days \(total 14 days\). - Aug 1 \(Fri\): 1 day \(total 15 days\). Non-working days: 6 - 0 holiday skipped - 3 weekends skipped: Aug 16–17; Aug 9–10; Aug 2–3
OptionDescription
PhasePhase 2: Development
Original end dateJul 31 \(Thu\)\(The day before the Phase 3 start date\)
Adjusted end dateJul 31 \(Thu\)\(a working day, no adjustment needed.\)
Original start dateJul 7 \(Mon\)\(25 days from the phase's adjusted end date, includes weekends and holidays\)
Adjusted start dateJun 26 \(Thu\)\(excludes weekends and holidays, see the End date calculation\)
Key datesSprint end: Every 10 working days from the phase's adjusted start – Jul 10 \(Thu\), Jul 24 \(Thu\)\(all working days, no adjustment needed\)
Original duration25 daysJul 7 \(Mon\) – Jul 31 \(Thu\)
Adjusted duration36 days \(25 working days + 11 non-working days\)Jun 26 \(Thu\) – Jul 31 \(Thu\)
End date calculationWorking days: 25- Jul 31-28 \(Thu-Mon\): 4 days. - Jul 25–21 \(Fri-Mon\): 5 days \(total 9 days\). - Jul 18–14 \(Fri-Mon\): 5 days \(total 14 days\). - Jul 11-7 \(Fri-Mon\): 5 days \(total 19 days\). - Jul 3-Jun 30 \(Fri-Mon\): 4 days \(total 23 days\). - Jun 27-26 \(Fri-Thu\): 2 days \(total 25 days\). Non-working days: 11 - 1 holiday skipped: Jul 4 \(Independence Day\) - 5 weekends skipped: Jul 26-27; Jul 19-20; Jul 12-13; Jul 5-6; Jun 28-29
OptionDescription
PhasePhase 1: Planning
Original end dateJun 25 \(Wed\)\(The day before the Phase 2 start date\)
Adjusted end dateJun 25 \(Wed\)\(a working day, no adjustment needed\)
Original start dateJun 16 \(Mon\)\(10 days from the phase's adjusted end date, includes weekends and holidays\)
Adjusted start dateJun 11 \(Wed\)\(excludes weekends and holidays, see the End date calculation\)
Key datesMidpoint: On fifth working day from the phase's adjusted start – Jun 17 \(Tue\)\(a working day, no adjustment needed\)
Original duration10 daysJun 16 \(Wed\) – Jun 25 \(Wed\)
Adjusted duration15 days \(10 working days + 5 non-working days\)Jun 11 \(Wed\) – Jun 25 \(Wed\)
End date calculationWorking days: 10- Jun 25–23 \(Wed–Mon\): 3 days. - Jun 20 \(Fri\): 1 day \(total 4 days\). - Jun 18–16 \(Wed-Mon\): 3 days \(total 7 days\). - Jun 13–11 \(Fri-Wed\): 3 days \(total 10 days\). Non-working days: 5 - 1 holiday skipped: Jun 19 \(Juneteenth\) - 2 weekends skipped: Jun 21-22; Jun 14-15
  • Summary Timeline

    The timeline extends beyond the 70-days original duration to account for weekends and associated holiday schedule, but the phase durations remain fixed in working days.

OptionDescription
Original calendar spanJul 8 to Sep 5
Image omitted: dpr-schedule-in-release-without.png
Calendar view of a release timeline without considering any holidays and weekends.
Adjusted span, excluding non-working daysJun 11 to Sep 5
Image omitted: dpr-schedule-in-release-with.png
Calendar view of a release timeline considering associated holiday schedule and weekends.
Original release duration60 working days
Adjusted release duration87 calendar days
Non-Working Days87 – 60 = 27 days \(12 weekends + 3 holidays\)

Parent Topic:Exploring Digital Product Release