Manage budget of your planning items in Strategic Planning
Allocate, manage, and approve budget for your planning items. Lean budgeting enables you to allocate budget for short planning cycles for different fiscal periods such as monthly, quarterly, or yearly breakdown level rather than allocating the budget to the complete duration of the planning item.
Before you begin
- As an Admin, enable the property to work on budgeting. For more information, see Enable financial budget allocation for planning items in Strategic Planning.
- As an Admin, configure the attribute to allocate and approve budget by cost type or expense type. For more information, see Configure budget attribute at instance-level.
- Role required: it_portfolio_manager
Procedure
Navigate to Workspaces > Strategic Planning Workspace and select portfolio plan.
Select a planning item from the Planning module.
Select the Financials tab.
Use the Display mode list and select Budget allocation.
Manage budget using one of the following ways for the selected time scale at monthly, quarterly, or yearly level.
- Double-click each cell in the Budget column to manually enter the value.
- Select Copy cost as budget from the Budget column options to copy Forecast value as budget. You can edit the budget values using the in-grid editing feature after copying Forecast to budget.
Note: Unapproved budget values are indicated with
Tick mark in a circle representing the unapproved budget icon.
- Select Approve budget (
Approve budget button.\).
Approve budget confirmation window is displayed. The **Create a financial baseline for this budget approval** option is enabled by default which captures the latest budget and financial estimates.
**Tip:** The financial baseline created while approving the budget can be compared with the future baselines once the actual expenses are captured to track financial performance.
- On the confirmation window, select Approve (
Approve button.\).
Result
Budget widget is updated to reflect the latest approved budget. Project Manager can view the approved budget and compare it with the planned costs using the budget vs cost view by cost type.