View unassigned tasks using Resource Management Workspace

Filter unassigned tasks to view custom requests to match with your organization's priorities and planning, and assign them to resources.

Before you begin

Procedure

  1. Navigate to Workspaces > Resource Management Workspace

  2. Select the Resource cards icon (

Image omitted: rmw-resource-cards-L1-icon.png
Resource cards icon.\) from the menu and open a resource card.
  1. Enable the Unassigned tasks toggle (
Image omitted: rmw-unassigned-tasks-toggle.png
Unassigned tasks toggle.\) to view the unassigned work requests in the lower tray.
Project Managers create resource requests based on the primary attributes \(Group, Skill, or Role\).
  1. In the bottom tray, select Filter (
Image omitted: filter-icon.png
Funnel symbol indicating the filter option.\) to filter the unassigned work and get a custom view of what you want to see.
You can use the attributes such as resource groups, teams, roles, skills, projects, time frame, and so on, to work with advanced filters.

**Tip:** Use the condition builder to build a filter and work on priority requests.

Example: This is a condition to filter the unassigned work requests created for a specific user.
Image omitted: rmw-unassigned-work-filter-condition.png
Filter condition to view the unassigned work for a specific resource.
  1. Select Filter.

    The unassigned work matching the filter condition is displayed in the Unassigned tasks tray.

Image omitted: rmw-rsrc-portfolio-view.png
Resource board view with assigned tasks in the top tray and unassigned tasks in the bottom tray.

Parent Topic:Using Resource Management Workspace