Update cost plan related to a resource plan

If a resource plan is associated to a project, project task, or demand and has a related cost plan, then a requester or a resource manager can update the related cost plan after updating the resource plan.

Before you begin

Role required: resource_user or resource_manager or it_project_manager or it_demand_manager

About this task

If a resource plan does not have a related cost plan, the Update Cost Plan related link is not displayed for the resource plan.

Procedure

  1. Save the updates to the resource plan.

  2. Click the Update Cost Plan related link.

    The cost plan associated to a resource plan is automatically updated as soon as the Planned cost in the resource plan is updated. The planned cost on resource plan gets updated when there is a change in:

    • Planned hours
    • User
    • State
    • Start and end dates

Result

The cost plan associated to the resource plan is updated as follows:

  • If the resource plan is in Planning or Requested state, planned hours is updated in the cost plan.
  • If the resource plan is in Confirmed/Allocated state and the Confirmed/Allocated hours are less than planned hours, then the higher of the planned cost and Confirmed/Allocated cost is updated in the cost plan.
  • If the resource plan is in Confirmed/Allocated state and the Confirmed/Allocated hours are equal to or more than planned hours, then the Confirmed/Allocated cost is updated in the cost plan.

Cost from resource plan will be interfaced to the unit_cost field on the Cost Plan [cost_plan] table.

Parent Topic:Resource plans

Related topics

Create a resource plan

Use Resource Finder to analyze resource availability

Create an operational resource plan

Request resources

Confirm a resource plan

Confirm and allocate a resource plan

Request a change to a resource plan

Recalculate costs of a resource plan

Complete an allocated resource plan

Cancel a resource plan

Delete a resource plan

Extend a resource plan

Request extension of an allocated resource plan

Allocate resources for the extended period

Reduce the duration of a resource plan

Time zones in resource plans

Associate a time card with a resource plan