Migrate resource plans and cost plans to Next Experience

Migrate resource plans and cost plans of your projects or demands to resource assignments and attribute-bases cost plans and work on the resource allocations and project financials using Project Workspace.

Before you begin

Procedure

  1. Use one of the following options to open a project or a demand.

    • To open a project, navigate to All > Project > Projects > All and open a project.
    • Too open a demand, navigate to All > Demand > Demands > All and open a demand.
    • Select the Migrate resource plans related link.

    Note: This selection triggers the migration of resource plans and cost plans simultaneously.

  2. In the Migrate Resource Plans confirmation window, select OK.

Image omitted: rp-ra-migration-confirmation-window.png
Resource plans migration confirmation window.
**Tip:** You can [Scheduled job to migrate resource plans and cost plans](migrate-rsrc-plan-cost-plan-scheduled-job.md).

Result

Resource plans are migrated to resource assignments, cost plans are migrated to attribute-based cost plans. Refresh the project page to view the resource assignments in Resource assignments related list.

What to do next

Create resource assignments to manage resource efforts.