Confirm and allocate a resource plan

After the resource plan is requested, as a resource manager, you can directly allocate the resources. To confirm and allocate, the resource plan must be in the Requested state.

Before you begin

Important: Resource plans in Resource Management will no longer be available for new customers from future releases.

You're encouraged migrate your existing resource plans to work on resource assignments which offers more flexibility and Create resource assignments in Resource Management Workspace using Resource Management Workspace or Project Workspace.

Resource managers can assign and approve the unassigned resource assignments using Resource Management Workspace.

Role required: resource_manager

About this task

Modify or cancel a resource plan that is in the Allocated state.

If the resource type in a resource plan is a group, you can request resources only if that group has active members.

Procedure

  1. Navigate to All > Resource > Resource Plans > Requested.

  2. Open the resource plan (Requested) that you want to confirm and allocate, and select Confirm and Allocate.

Result

The resource plan automatically moves to the Allocated state from the Requested state. Soft allocations are converted to hard allocations when the resource plan moves to the Allocated state.

Any errors or warnings during allocations are logged in the Resource Plan Logs related list on the Resource Plan form. The log is generated if a resource is allocated over 24 hours for a given day. You can review these logs to take correct actions for further resource allocation.

Parent Topic:Resource plans

Related topics

Create a resource plan

Use Resource Finder to analyze resource availability

Create an operational resource plan

Request resources

Confirm a resource plan

Request a change to a resource plan

Recalculate costs of a resource plan

Update cost plan related to a resource plan

Complete an allocated resource plan

Cancel a resource plan

Delete a resource plan

Extend a resource plan

Request extension of an allocated resource plan

Allocate resources for the extended period

Reduce the duration of a resource plan

Time zones in resource plans

Associate a time card with a resource plan