Managing projects with Project Workspace

Use the features of Project Workspace to plan and manage your project.

Image omitted: project-workspace-homepage.png
project-workspace-grid-view
Image omitted: project-workspace-listview.png
project-workspace-list-view

The homepage contains the following UI components to help you navigate through the workspace.

FeatureDescription
Grid view of projects \(
Image omitted: grid-view-homepage-icon.png
grid view of projects.\)
Opens the project in grid view or card view.
List view of projects \(
Image omitted: list-view-homepage-icon.png
list view of projects.\)
Opens the project in list view.
My ProjectsThis section displays all the projects that you own, including subprojects.
All ProjectsThis section displays all projects in the system. All projects include projects from customer projects, team spaces, and audit.
ProjectsThis section displays only projects.
SubprojectsThis section displays only subprojects.
Project cardsEach project is represented by a project card. These cards display high-level details, such as the project name, status, planned dates, and the manager that the project is assigned to.
Project searchOption to search for projects by name or by the user it’s assigned to.
FilterOption to apply filters on the homepage. The filter preferences that you choose are retained in the filter criteria.
RefreshReloads the homepage.
Create from templateOption to create a project from template.
NewOption to create a project.

Planning header

The header displays the project name and provides the following various options.

NameDescription
Edit project details \(
Image omitted: icon-edit.png
Edit icon.\)
Opens the project details in the side panel to edit. See Create a project from Project Workspace.
Activity \(
Image omitted: icon-activity.png
Activity icon.\)
Facilitates conversation between different stakeholders. See Collaborate with stakeholders from Project Workspace.
Attachments \(
Image omitted: icon-attachments.png
Attachments icon.\)
Enables you to add files to the project. See Collaborate with stakeholders from Project Workspace.
Refresh the project \(
Image omitted: icon-refresh.png
Refresh project workspace.\)
Reloads the planning page.
Save \(
Image omitted: icon-save.png
Save.\)
Saves your changes. This button is inactive by default to facilitate auto-save of any changes made to the project plans. Enable or disable the auto-save functionality from the Advanced tab of the Settings \(
Image omitted: icon-settings.png
Settings icon.\) panel.
Resources not synced \(
Image omitted: resources-not-synced-icon.png
resources-not-synced-icon\)
Enables you to synchronize the project and resource assignment dates. When there’s a change in the planned or actual dates of the project tasks, this icon is enabled. When the project has classic resource plans, this icon is inactive by default.
Image omitted: resource-plan-toggle.png
resource-plan-toggle
Enable this toggle to display the resource assignment pane.
Image omitted: all-view-button.png
all-view-button
Displays data in both grid and gantt view on planning page. This button is active by default.
Image omitted: gantt-view-button.png
gantt-view-button
Displays data in Gantt view on planning page. Use this button to change task dates and dependencies.
Image omitted: grid-view-button.png
grid-view-button
Displays data in Grid view on planning page. Use this button to add and delete tasks, change task dates and dependencies, and assess the progress of the overall project.
Baselines \(
Image omitted: icon-baselines.png
Baselines option.\)
Enables you to create and compare schedule and financial baselines. See Create and compare project baselines in Project Workspace.
Critical path \(
Image omitted: icon-critical-path.png
Critical path.\)
Toggle the button to switch on/off the display of the critical path of the project.
Image omitted: workspace-critical-path.png
Project critical path.
Add Task
Image omitted: workspace-add-task.png
Add project task.
Adds a project task in the data grid. See Create and assign project tasks from Project Workspace.
Project actions \(
Image omitted: more-actions-homepage-icon.png
more-actions-icon.\)

Provides other actions to perform on the project.

  • Apply template
  • Delete project
  • Move project
  • Duplicate project
  • Import from MS project
  • Export project
  • Launch help video
  • Calculate Completion Estimates
  • Copy partial project

Image omitted: workspace-more-actions.png
More actions menu.</p>

Synchronize the project's date with the start dates of the associated resource plans, cost plans, benefit plans, resource assignments, project tasks, and subprojects using Move Project.

Resource assignment pane

The resource assignment pane contains the following UI components to help you manage your resources from Project Workspace.

NameDescription
Refresh the resource assignment \(
Image omitted: icon-refresh.png
Refresh project workspace.\)
Reloads the selected assignment and allocation.
Image omitted: allocation-heatmap-toggle.png
allocation-heatmap-toggle
Displays the resource allocation in the resource assignment pane.
Image omitted: effort-type-dropdown.png
effort-type-dropdown
Displays the effort type as FTE, Hours, or Person days.
Image omitted: month-week-dropdown.png
month-week-dropdown
Displays the effort by week or month. This button is displayed only when the Allocation heatmap toggle is enabled.
Image omitted: add-resource-button.png
add-resource-button
Add a resource in the resource assignment pane.

Data grid

The data grid shows the list of project tasks and subprojects in rows, and the following options to perform actions on the rows. If a project has subprojects, you can drill down into the tasks and scheduling of these subprojects too.

OptionDescription
Column actionsSort and filter the project tasks using the actions on the header. Point your mouse device to a column header to see the context menu icon \(
Image omitted: icon-row-context-menu.png
Row context menu.\).
Using this menu, you can perform actions such as autofit, hide, or reset. If you select the context menu \(
Image omitted: icon-row-context-menu.png
Row context menu.\) for certain columns, such as Short description or State, you can also filter the project task rows.
Image omitted: workspace-column-actions.png
Column context menu.
Rearrange rows \(
Image omitted: icon-rearrange.png
Rearrange rows.\)
Enables the dragging of the project task rows to a position of your choice on the grid.
Select row \(
Image omitted: icon-select.png
Select row.\)
Choose to select multiple project task rows at once. Use the row context menu \(
Image omitted: icon-row-context-menu.png
Row context menu.\) to perform various actions.
Row context menu \(
Image omitted: icon-row-context-menu.png
Row context menu.\)
Provides various actions for the selected rows, such as edit task, add task above or below, delete row, add dependency, and more. You can also select multiple rows and perform an action on them at once, using the row context menu. For example, indenting or deleting multiple tasks.
Image omitted: row-context-menu.png
row-context-menu
Expanded row \(
Image omitted: icon-expanded-row.png
Expanded row.\)
Indicates that a project task row is expanded to show its child tasks. Select this icon to collapse the row and hide the child tasks.
Collapsed row \(
Image omitted: icon-collapsed-row.png
Collapsed row.\)
Indicates that the project task contains child tasks. Select this icon to expand the row and view the child tasks.
Reorder column \(
Image omitted: reorder-column-icon.png
reorder-column-icon\)
Reorders the columns of the data grid.
Edit an individual cellEdit or copy the info of this cell by selecting the cell context menu \(
Image omitted: icon-row-context-menu.png
Context menu.\) or select and hold \(or right-click\) a cell.
Use this menu to copy and paste cell contents, add dependencies, add project tasks directly above or below this cell position, or delete the whole row.
Edit multiple cellsBulk-edit cells by selecting multiple cells and select and hold \(or right-click\) one of the cells. You can also use the cell context menu \(
Image omitted: icon-row-context-menu.png
Context menu.\) for more options.

Selecting a project task by selecting its short description opens the task details in a side panel, enabling you to edit them. See Update a project task from the Project Workspace.

You can also increase or reduce the area occupied by the data grid by dragging the line that separates them.

Timeline view

The timeline view shows the project timeline based on its planned start and end dates, and displays the project task bars and milestones.

By using the planning settings (

Image omitted: icon-settings.png
Settings icon.\), you can choose to display the bar labels, dependency lines, and the critical path. See [Personalize the planning page view in Project Workspace](personalize-planning-console-in-project-workspace.md).

Project timeline

The timeline shows the planned period of the project. You can reduce or increase the visibility of the project period by changing the timescale to Year, Quarter, Month, Day, or Week. Select the timescale icon (

Image omitted: icon-timesclae.png
Timescale icon.\) and choose an option.

The timescale view that you choose is saved in the preferences.

Dependency lines

These lines show the dependencies between the project tasks. You can add new dependencies by drawing them on the timeline view, or select an existing dependency to edit its details in the side panel. See Add internal project task dependencies from Project Workspace. The dependencies that you choose are saved in the preferences.