Update task dependency details in Project Workspace
Update the details of the dependency including its type and lag time from Project Workspace.
Before you begin
Role required: it_project_manager
Procedure
Open a project from the home page of Project Workspace.
For information, see Access the Project Workspace.
Open the dependency side panel in one of the two ways.
Option Action From the data grid From the dependency column, select the dependency of the task. From the timeline view Select the dependency line. Edit the fields.
Select Update.
Parent Topic:Add internal project task dependencies from Project Workspace