Assign a project schedule

Without an assigned schedule, a project calculates a day as a full 24 work hours. To schedule tasks by a more realistic work day, assign a schedule to the project. If the schedules provided in the base system do not suit your needs, define a new one.

Before you begin

Role required: it_project_manager

Procedure

  1. Open a project.

  2. If the Default view is active, right-click the header bar and select View > Advanced.

  3. Select a schedule in the Schedule field and select Save.

Parent Topic:Starting a project

Related topics

Create a project task from a project

Create a parent-child relationship on the Project Task form

Create a monetary benefit plan for a project

Create a non-monetary benefit plan for a project

Associate monetary and non-monetary benefit plans

Create a project cost plan

Recalculating costs of all resource plans in a project

Create an expense line

Create and manage waterfall projects

Update a project

Copy a project

Create baseline of a project

Create a milestone

Activate project task email notifications

Change the planned start date of a project

Create a cost type definition

Costing add-on in Project Management

Generate labor costs

Create a project status report

Allocate budget to a project

Migrate budget of active projects to Next Experience

Migrate financial baselines of projects to Next Experience