Modify a project task dependency
Modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.
Before you begin
Role required: it_project_manager
About this task
Project task dependencies are saved on the Planned Task Relationship [planned_task_rel_planned_task] table. You can access dependencies from the planning console.
Procedure
Double-click a dependency on the Gantt chart of the planning console.
On the form, fill in the details.
For more information, see Planned Task Relationship form.
Image omitted: planned\_task\_relationshipform.png
Planned Task Relationship form
Planned Task Relationship form
Select Update.
You can view dependencies in the Project Task related list on a Project or Project Task form and from the Project Tasks list on the workbench. These columns show the dependencies:
- The Dependency column shows the successor task in the relationship.
- The Dependencies column shows the dependency value. See Predecessor dependencies in the planning console for a description of what you see in this column.
Parent Topic:Create a dependency from the planning console