Create a project task in the project workbench
Create a project task for a waterfall phase.
Before you begin
Role required: it_project_manager
About this task
While creating a project task in the project workbench, the time constraint type is defaulted based on the project type.
- For a manual project, the default constraint is Start On and cannot be changed.
- For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required.
- When the constraint is Start ASAP, the Planned start date is disabled.
- When you create an agile phase and associate a sprint, the start date of the task is set from the sprint start date and the constraint becomes Start On automatically.
Procedure
Select a waterfall phase in the project workbench timeline.
Select New in the detail view.
Fill out the Project Task form.
Select Submit.
Parent Topic:Managing Project workbench