Create a parent-child relationship on the planning console
The WBS section of the planning console allows you to create parent-child relationships for new tasks or move around existing tasks in a new parent-child relationship. The position of a task in the hierarchy and the level of indentation determine the parent-child relationship it has with the tasks above or below it.
Before you begin
Role required: it_project_manager
About this task
In this example, the System Readiness Assessment task is a child of the Planning task because it is one level below the Planning task and is indented.
Parent-child task example
Procedure
Select a task in the WBS section of the planning console to highlight it.
Select a combination of any of the following icons to create the task and move it or move the other tasks to create the required hierarchy:
Icon Action Add task above icon (
Add task icon\)|Create a task above the highlighted task.|
|Add task below icon \(
Add task icon\)|Create a task below the highlighted task.|
|Indent icon \(
Indent icon\)|Makes the highlighted task a child of the task above it.|
Parent Topic:Using Planning console - Legacy
Related topics
Open the project planning console
Predecessor dependencies in the planning console