Create a milestone
A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones.
Before you begin
Role required: it_project_manager
About this task
Note: Milestones cannot be shared between projects unless one project is nested under another project.
Procedure
Create a project task and give the Duration field a value of 0.
Open the planning console Gantt chart and verify that it appears as a diamond.
You can also convert a task to milestone through Planning console tasks.
Parent Topic:Starting a project
Related topics
Create a project task from a project
Create a parent-child relationship on the Project Task form
Create a monetary benefit plan for a project
Create a non-monetary benefit plan for a project
Associate monetary and non-monetary benefit plans
Recalculating costs of all resource plans in a project
Create and manage waterfall projects
Activate project task email notifications
Change the planned start date of a project
Costing add-on in Project Management
Create a project status report