Create a milestone

A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones.

Before you begin

Role required: it_project_manager

About this task

Note: Milestones cannot be shared between projects unless one project is nested under another project.

Procedure

  1. Create a project task and give the Duration field a value of 0.

  2. Open the planning console Gantt chart and verify that it appears as a diamond.

    You can also convert a task to milestone through Planning console tasks.

Parent Topic:Starting a project

Related topics

Create a project task from a project

Create a parent-child relationship on the Project Task form

Create a monetary benefit plan for a project

Create a non-monetary benefit plan for a project

Associate monetary and non-monetary benefit plans

Create a project cost plan

Recalculating costs of all resource plans in a project

Create an expense line

Create and manage waterfall projects

Update a project

Copy a project

Assign a project schedule

Create baseline of a project

Activate project task email notifications

Change the planned start date of a project

Create a cost type definition

Costing add-on in Project Management

Generate labor costs

Create a project status report

Allocate budget to a project

Migrate budget of active projects to Next Experience

Migrate financial baselines of projects to Next Experience