Create a project cost plan
Create a cost plan to specify the unit cost of a cost type for a fiscal period. Project cost plans capture the costs of projects.
Before you begin
Role required: it_project_manager
Application required: Project Portfolio Management with Financials
About this task
The application automatically creates cost plan breakdown records when you save the cost plan. Cost plans can also have associated expense lines.
Note: Cost plans are automatically created for resource plans that are associated to projects and project tasks.
To use multiple currencies, create a new cost plan for another currency.
Procedure
Open the project form.
From the related links, select Cost Plans.
Select New.
Note: To create a cost plan from the Financials tab in Project Workspace, select Manage.
On the form, fill in the fields.
For field information, see Cost Plan form.
Note: When you change the planned start date of a project, the associated cost plans and resource plan also change. The project property Change Resource Plan and Cost Plan Start Date with Demand or Project Start Date Change controls the behavior for project start date change.
Select Submit.
What to do next
To recalculate the values in the Estimate at Completion field, use the Calculate Estimate at Completion related link. To view the cost plan breakdowns, select the Cost Plan Breakdowns related list.
- Update a cost plan breakdown
Update a cost plan breakdown record that specifies the estimated and actual cost, at a granular level, for specific fiscal periods. - Enable cost rollup calculations
Enable rollup calculations from the project properties. - View actual project costs
When you are using Project Portfolio Management with Financials, you can view actual project costs on cost plans and projects.
Parent Topic:Starting a project
Related topics
Create a project task from a project
Create a parent-child relationship on the Project Task form
Create a monetary benefit plan for a project
Create a non-monetary benefit plan for a project
Associate monetary and non-monetary benefit plans
Recalculating costs of all resource plans in a project
Create and manage waterfall projects
Activate project task email notifications
Change the planned start date of a project
Costing add-on in Project Management
Create a project status report
Migrate budget of active projects to Next Experience