Copy an existing task or project
Save time when building a project by copying tasks from other projects.
Before you begin
Role required: it_project_manager
About this task
The Copy partial project option copies a selected task and its child tasks into the project, or all project tasks into a sub-project. It also preserves all dependencies and relationships among the copied tasks and their child tasks. Any relationships or dependencies that involve tasks outside of the scope of the copied task are not preserved.
Procedure
In the Project or Project Task form, right-click the header bar and select Copy partial project.
In the Task field, select a project task or project to copy.
By default, projects begin with PRJ and project tasks begin with PRJTASK.
Enter a Name for the new project or task.
Select OK.
The copied task is added to the current task or project. If a project was copied, then all the tasks are inserted into a new sub-project.
Result
The copied tasks are inserted as a child of whatever task or project that you are currently viewing. Actual duration and the actual start and end dates are reset to null values. The state is set to New and percent complete is set to 0.
By default only the short description, planned dates and duration fields are copied from source project to the target project. If additional columns must be copied, they should be declared in the project property List of attributes that will be copied from the originating project task.
- Change default values of copied fields
Change the default values of in the new partial project.
Parent Topic:Create a project task from a project