Create a program task

You can create program tasks from the Program form related lists.

Before you begin

Role required: it_program_manager

About this task

Procedure

  1. Navigate to Project > Programs > All.

  2. Select the program from the list.

  3. In the Program Tasks related list, click New.

  4. Fill out the form fields (see table).

    There are a few fields that are populated after the task is created.

  5. Click Submit.

Result

The new task appears in the Program Task related list on the Program form.

FieldDescription
Short description\[Required\] A brief description of the program task.
NumberA system generated number with a configurable prefix.
StateThe current state of the program. The states include: Pending, Open, Work in Progress, Closed Complete, Closed Incomplete, Closed Skipped.
Planned start dateThe estimated date and time for the program task to start.
Planned end dateThe estimated date and time for the program task to end.
Planned durationThe estimated length of time \(from start time to end time\) of the program task.
Assigned toThe user assigned to the program task.
MilestoneA milestone is a program task with a duration of zero \(0\). Use milestones to mark key dates in your program, such as key decision points or approvals.
Key milestoneYou can define a milestone as a key milestone to track the program progress. For example, you can create key milestone for completion of deliverables such as a program plan. A key milestone is visible on the program timeline.
DescriptionA detailed description of the program task.
Additional comments \(Customer visible\)Enter information that you want the users to see.
Work notesEnter work notes about the milestones, impediments, or changes as the program progresses.Note: Users with the business stakeholder role for PPM can view this field. For more information, see Business stakeholder role for PPM.
FieldDescription
Actual start dateThe date that this program started. This date is populated after you update the program state to Work in Progress.
Actual end dateThe date that this program ended. This date is populated after you update the program state to Closed Complete.
Actual durationThe actual duration of the program from program start to program closure. As with planned duration, the actual duration shows total program time.

Parent Topic:Create a program to manage projects and demands