Realign resource assignments for demands
Planning and execution of your roadmap involves change in priority or timelines of your work. In such cases, you can adjust the resource assignment dates to match with the latest dates of your demands.
Before you begin
Migrate resource plans to resource assignments
Role required: it_demand_manager
Procedure
Open a demand from the home page of Next Experience for Demand Management.
For more information, see Access demands.
Select Details from the L-2 (level 2) navigation menu.
Change the Approved start date and Planned start date to meet your organizational priorities.
Select Save.
Select the More Actions option and select Realign assignments to demand.
Result
In the Resource assignments tab, you can see the Start date of the resource assignments aligned with the demand start dates.