Skip to content
Release: Australia · Updated: 2026-03-12 · Official documentation · View source

Data migrated from a demand to a created project

Data fields are migrated from a demand to a project when the project is created from the demand.

Field typeDescription
DemandThe following demand fields are migrated to a project:- Description - Business case - Investment Class - Investment Type - Risk of performing - Risk of not performing - Enablers - Barriers - In scope - Out of scope - Assumptions - Business Unit - Department - Impacted Business Units - Business Capabilities - Priority - Impact - Rate Model - Approved start date - Approved end date - Short description - Program - Domain - Goals - Strategies - Impacted Business Applications - Configuration item - Company - Urgency - Project Manager - Project currency - Project calculation
Resource assignmentsResource assignments are migrated to a project by updating the task reference from the demand to project.
RequirementsDemand requirements.
Financial recordsFinancial records such as cost plans and breakdowns, benefit plans and breakdowns \(monetary and non-monetary\), and demand budgets are migrated to a project. This process updates the task reference from demand to project.
RIDACRIDAC entities are migrated to a project by updating the task reference from demand to project. The migrated entities include the risks, issues, decisions, project actions, request changes, and RIDAC\_m2m records.
AssessmentThe following assessment data fields are migrated to a project:- Risk - Value - Score - T-Shirt size
StakeholdersStakeholder records.
Project Currency FinancialIf the multicurrency feature is active, the project financial fields are calculated according to the project currency and reference rate.

Parent Topic:Data migrated from demands to artifacts