Map hardware assets to an operational schedule

Create an asset schedule to map the hardware assets to an operation schedule.

Before you begin

Role required: admin

About this task

An asset schedule record is stored in the Asset schedule policy [sn_asset_cmn_schdule_policy] table.

Note: If an asset isn't associated with an operational schedule, the Default asset schedule (24 hours, 7 days a week or 24/7) will be applied.

The Asset performance - Map schedule policies job runs weekly to sync the mapping between assets and the operational schedule.

Procedure

  1. Navigate to Workspaces > Hardware Asset Workspace > Asset operations > KPI configuration.

  2. From the KPI configuration list, select Asset schedules.

  3. Select New.

  4. On the form, fill in the fields.

FieldDescription
NameUnique name for the asset schedule.
Source tableSource table for the assets. You can select any of the following tables:- Hardware \[alm\_hardware\] - Enterprise asset \[sn\_ent\_asset\] - Construction asset \[sn\_ent\_construction\_asset\] - Facility asset \[sn\_ent\_facility\_asset\] - Industrial asset \[sn\_ent\_industrial\_asset\] - Linear asset \[sn\_eam\_linear\_asset\] - Medical asset \[sn\_ent\_medical\_asset\] - Retail asset \[sn\_ent\_reatail\_asset\] - Tactical equipment asset \[sn\_ent\_tactical\_asset\] - Transportation asset \[sn\_ent\_transportation\_asset\] - Wearable asset \[sn\_ent\_wearable\_asset\]
ConditionSet a condition to select the assets that you want to associate with the operational schedule. For example, if you set the Department field to IT, the operational schedule is inked to all assets within the IT department.Note: Select the source table before setting the condition.
ScheduleOperational schedule that you want to associate with the assets.
PriorityOrder in which schedules should be applied to an asset when there are overlapping schedules.
ActiveIndicates whether the asset schedule is active.
  1. Select Save.

  2. To sync the mapping between the assets and the operational schedules on demand, select Sync KPI records.