The following table describes the field values for the Industrial Guided Task form.

FieldDescription
NumberSystem-generated unique number for the task.
PriorityOptions are:- 1 - Direct - 2 - This shift - 3 - Today - 4 - Within 7 days - 5 - Within 30 days - 6 - Unplanned
Short descriptionAuto-populated with the name of the standard from which the task is being created.
Work notesAdditional information and comments that can help execute the task successfully.
Assignment groupGroup of users that the task can be assigned to.
Assigned toUser that the task has been assigned to.
Functional locationIndustrial facility work area where the task is to be completed. Defined using the ISA-95 standard as an operational model site. Automatically filled based on the logged-in user's worker profile.
EquipmentMachine to which the task relates. This field is already populated if the equipment is specified in the standard.
Planned startPlanned start of the task execution.
Planned endPlanned end of the task execution.Note: If you create a task without a planned end date, the system automatically sets the planned end to match the due date. This automatic population enables the embedded dashboard to use the planned end data for calculations, such as measuring the percentage of tasks closed in time.
Due dateThe date by which the task is to be executed. If not set, it’s calculated based on priority. For more details, see Due date calculation.

Parent Topic:Industrial Guided Tasks reference