Skip to content
Release: Australia · Updated: 2026-03-12 · Official documentation · View source

Create a risk event task

A risk event might require associated tasks. Unless these tasks are created and eventually closed, the risk event cannot be closed.

Before you begin

Role required: sn_risk.manager

Procedure

  1. Navigate to All > Risk Events > All Events.

  2. Select the record for which a task must be created.

  3. Select the Tasks related list and then select New.

  4. On the form, fill the fields.

    FieldDescription
    Assigned toPerson that the task is assigned to.
    PriorityLevel of importance given to a task, which indicates how readily a task or assignment can be delayed.
    Short descriptionBrief description of the task.
    DescriptionDetailed description of the task.
    Work notesAny relevant information for your reference.
    Additional commentsAny additional information that might be necessary.
  5. Select Submit.

What to do next

Review the associated issues of a risk event or create a new issue during approval. For more information, see Manually create GRC issues.

Parent Topic:Use Risk Events