Skip to content
Release: Australia · Updated: 2026-03-12 · Official documentation · View source

Create a control test from an engagement

After defining a control, audit managers create control tests that run periodically and provide documented evidence of whether the associated control is operating correctly.

Before you begin

Role required: sn_audit.admin and sn_audit.manager

Procedure

  1. Navigate to All > Audit > Engagements > All Engagements.

  2. Open the engagement for the audit task you want to create.

    Assign audit tasks to engagement in one of the following states:

    • Validate
    • Fieldwork
    • Awaiting approval
    • In the Audit Tasks Related List, click New.
  3. In the Audit Tasks Interceptor, click Control Test.

  4. On the form, fill in the fields.

FieldDescription
NumberUnique identification number.
State- Open - Work in Progress - Review - Closed Complete - Closed Incomplete - Closed Skipped
ParentParent audit task.
Control effectivenessControl effectiveness.
Assigned toUser assigned to this control test.
IssueIssue related to this control test.
Test planTest plan associated with this control test.
Short descriptionBrief description of the control test.
Schedule
Planned start dateIntended date the control test should begin.
Planned end dateIntended date the control test should end.
Planned durationExpected duration of this control test. As with actual duration, the planned duration shows total activity time and takes the control test schedule into consideration.
Actual start dateDate that this control test began.
Actual end dateDate that this control test ended.
Actual durationDuration of the control test from control test start to control test closure.
Design test
Design effectiveness- Effective - Ineffective
Design expectationsBasic requirement that should be met by a control so that it is effective. This checks if the control was designed properly to achieve the control objective.
Design assessment proceduresProcedure or steps to be followed to conclude whether the design of the control is effective to achieve the control objective or not. This is based on the design expectation.
Design resultsResults of testing the design of the control based on the design assessment procedure.
Operation test
Operation effectiveness- Effective - Ineffective
Operation expectationsExpectations that should be met to ensure that the control is operating effectively to achieve the control objective.
Operation assessment proceduresDetailed steps, to carry out the operation expectations, which need to be performed to conclude that the control is operating successfully.
Operation resultsResults of testing the operation of the control based on the operation assessment procedure.
Activity journal
Work notesComments that are viewable by the audit manager.
Additional commentsCustomer-viewable comments.
Confidentiality
ConfidentialOption to enable confidentiality of the record. Only the assigned confidential users or confidential groups of users can access the record.For more information on confidential option, see Confidentiality flag for audit and compliance records.
  1. Click Submit.

  2. Automatically generate control tests from an engagement
    After adding an entity to an engagement, you can automatically generate control tests.

Parent Topic:Manage engagements