Create a milestone for an engagement

Create a milestone for an engagement to track the progress of an engagement. You can also add audit tasks to a milestone.

Before you begin

Role required: sn_audit.manager, sn_audit_ws.supervisor

About this task

A milestone is used to track the progress of an engagement.

After you create milestones for an engagement, you can also add audit tasks to the milestone. You can track those tasks as milestones.

You can assign a milestone to a user who is responsible for the milestone. The assigned user must have the sn_audit.user role. The assigned user then receives a notification about the assignment.

If an engagement moves to the Follow Up state, and if there are no open audit tasks, open milestones, or open observations, then the engagement moves to the Closed state.

Procedure

  1. Navigate to All > Audit > Audit Workspace.

  2. Select the lists icon (

Image omitted: ListsIcon.jpg
List icon.\).
  1. Select All engagements or My engagements in the Execution list.

  2. Select the link to the engagement record in the Name column.

  3. Select the Milestones tab.

  4. Select New.

  5. On the form, fill in the fields.

FieldDescription
NumberUnique number of the milestone. This number is automatically generated.
NameName of the milestone.
ParentParent engagement of the milestone.
TypeAudit milestone type. The choices are:- Scoping - Planning - Fieldwork - Follow up - Reporting - Closure
StateState of the milestone. The default state is Open.
Percent completePercentage of milestone completed.When a value is entered in this field, the state changes to Work in progress.
Key milestoneOption to mark the milestone as important.
Auto complete and closeOption to mark the milestone as close complete when all the associated audit tasks are completed and closed.If this option is enabled, then the percent complete is automatically updated according to the number of tasks marked as closed complete.
DescriptionBrief description of the milestone.
Assignment
Assignment groupGroup responsible for the milestone.The group members must have the sn\_audit.user role assigned.
Assigned toPerson responsible for working on the milestone.
Schedule
Due dateExpected completion date of the milestone.
Completion dateActual completion date of the milestone.
Closed dateActual close date of the milestone.
Activity
Additional commentsComments that customers can also view.
Work notes \(Private\)Comments that only the administrator and audit supervisor can view.
  1. Select Save.

    You can view the description of the Milestone record and monitor its status in the State banner of the default Overview page.