Transfer part orders through the Field Service Contractor Portal
Use a transfer order to move required parts between company stockrooms or to a location where a requesting agent can receive the parts.
Before you begin
Role required: wm_ext_manager
About this task
You can process only transfer orders that contain parts sourced from a warehouse that you manage.
Procedure
Navigate to All > Field Service Contractor Portal > My Lists > Transfer Orders.
Select a transfer order to transfer the asset.
From the Transfer Order Line related list, select a transfer order line.
From the Transfer Order Line Tasks related list, select a transfer order line task that is ready for fulfillment.
Eligible tasks have the short description text "Ready for fulfillment" and the state Open.
Click Close Task to complete fulfillment and start the asset transfer process.
The transfer order line task that was ready for fulfillment moves to the Closed Complete state.
The system automatically creates two new transfer order line tasks:
- The short description text for the transfer order line task to prepare for shipment is "Prepare for shipment" and the state is Open.
- The short description text for the transfer order line task for drop off is "Receive" and the state is Open.
- Drop off or prepare for shipment.
| To | Do this |
|---|---|
| Prepare for shipment | When you are ready to ship the asset: 1. Click and open the transfer order line task created to prepare for shipment. This task has the short description text "Prepare for shipment' and the state Open.
The system automatically does the following:
This task has the short description text "Ship" and the state Open.
This task automatically moves to the Closed Complete state.
This task has the short description text "Receive" and the state Open.
This task automatically moves to the Closed Complete state.
This task has the short description text "Deliver" and the state Open.
This task automatically moves to the Closed Complete state. |
| Drop off | When you are ready to drop off the part or asset:1. Click and open the transfer order line task created for drop off. This task has the short description text "Receive" and the state Open.
The system automatically moves the transfer order line created to prepare for shipment to the Closed Skipped state.
This task has the short description text "Delivery" and the state Open.
The task moves to the Closed Complete state. |