Skip to content
Release: Australia · Updated: 2026-03-12 · Official documentation · View source

Run a planned work schedule on demand

Planned work schedules mainly run using the Planned Maintenance Nightly Run scheduled job. However, you can make the schedule to run immediately or change the date when a schedule should run, if needed.

Before you begin

Role required: admin

About this task

When you run a planned work schedule on demand, all of the next run dates for the relevant planned work records are updated to the user-defined time, now or in the future. All the appropriate work orders are created. If the schedule is meter, condition, or script-based, work orders are created for work plan records that meet the schedule criteria.

Procedure

  1. Navigate to All > Field Service Management > Planned Work Management > Plans.

  2. Open a work plan that contains the schedule to run.

  3. In the Planned Work Schedules related list, select the maintenance schedule you want to run.

  4. In the Related Link section, select Run on demand.