Skip to content
Release: Australia · Updated: 2026-03-12 · Official documentation · View source

Create a new schedule

Create a schedule or modify an existing schedule to calculate the due date for metric data tasks.

Before you begin

Role required: admin

About this task

Using schedules, you can specify that the due date for a metric data task. For example, you can specify that the due date does not fall over a weekend or a holiday. Another example could be that you can specify your working hours so that the due date automatically is set based your specifications. By default, the 8-5 weekdays schedule is used to set the due date.

Procedure

  1. Navigate to All > Operational Sustainability Management > Administration > Schedules.

  2. Select New and provide a unique and meaningful Name and Description, and then fill in the form.

    For detailed information on Schedule form fields, see Schedule fields.

Parent Topic:Configure Operational Sustainability Management (formerly ESG Management)